Assess the location (visibility, distance, angle, height).
Check power supply availability and load capacity.
Confirm internet/network connectivity (LAN, 4G, WiFi).
Inspect the structure to ensure it can support the LED screen’s weight & wind load.
Take measurements for screen size and mounting design.
Design a steel frame or wall mount (engineer-approved).
Ensure structure is stable, rust-proof, and weather-resistant.
Mark the positions for mounting brackets and cable entries.
Install AC power lines with circuit breakers and surge protection.
Lay data cables (CAT6 / Fiber) for signal transmission.
Ensure proper grounding/earthing to protect against lightning and power surges.
Hoist and fix LED display cabinets one by one, starting from the bottom row.
Align cabinets precisely using levels & alignment tools.
Secure them tightly to withstand wind & vibration.
Install LED modules into each cabinet.
Connect power cables (from PSU to modules).
Connect data cables (from receiving card to modules).
Ensure module flatness & uniformity.
Install receiving cards inside the LED cabinets.
Connect them to the sending card or video processor in the control room.
Configure screen layout using LED control software.
Power on and check each cabinet/module.
Perform brightness & color calibration for uniform display.
Run test patterns to verify pixel mapping & resolution.
Check signal redundancy and backup power (if applicable).
Seal cabinet gaps with rubber gaskets / waterproof tape.
Ensure all cable entries are weatherproof.
Apply anti-rust coating on exposed steel structures.
Set optimal brightness levels for outdoor conditions.
Adjust viewing angle & content scaling.
Schedule automatic power on/off if supported.
Provide client training for basic operation & content upload.
Share maintenance guidelines (cleaning, fan checks, spare parts).
Schedule regular inspections (monthly or quarterly).
Regular cleaning of LED modules & fans.
Checking power supply & signal cables.
Replacing faulty modules/cards when needed.
Performing monthly or quarterly inspections.
It depends on screen size and site preparation. On average:
Small (10–20 sqm): 2–4 days
Medium (30–50 sqm): 1–2 weeks
Large (100+ sqm): 3–6 weeks
Content can be uploaded via:
USB / Laptop (direct connection)
Wi-Fi / LAN network
4G/5G control system
Cloud-based software (remote management)